How are Indian ports and airports using battery energy storage?

Ports are the early movers: V.O. Chidambaranar Port has tendered a 2 MWh battery and an 8 MW wind project with 5 MWh of storage, Chennai Port has tendered solar with storage, and Kandla's first electric tug carries a 4.4 MWh battery. Airports have mostly gone green through solar and renewable sourcing, with storage still emerging.

Published 19 November 2026 · Last updated 19 November 2026 · 5 min read · By NEXGY Research Desk

On this page

Ports and airports look like natural homes for battery energy storage systems (BESS). They are big, fenced, power-hungry sites with plenty of roof and land for solar, and an outage at either is expensive and very public.

In India the two are moving at different speeds. Ports have started writing batteries into tenders. Airports have gone green mostly through solar and renewable power purchase, and storage is the step that has not quite arrived yet.

Why ports are moving first

The push comes from policy. The Ministry of Ports, Shipping and Waterways’ Harit Sagar Green Port Guidelines, issued in 2023, set a target for major ports to draw more than 60% of their energy from renewables by 2030 and at least 90% by 2047. The same guidelines ask ports to build shore-to-ship power in phases, so berthed ships can switch off their diesel engines and plug in.

That combination creates exactly the problem storage solves. Solar peaks at midday. Ship arrivals, crane cycles and night-time operations do not follow the sun. And port loads are lumpy: a quay crane draws heavy power for a lift, then very little, then heavy power again.

What has actually been tendered

The clearest examples so far are in Tamil Nadu and Gujarat:

Port storage in India: from tender to tugOct 2025Feb 2026Q4 2026Nov 20262 MWhBESS tenderV.O. ChidambaranarPort, Thoothukudi5 MWh+ 8 MW wind tenderV.O. ChidambaranarPort, Thoothukudi4.4 MWhelectric tug batteryDeendayal Port,KandlaSolar + BESSRESCO tenderChennai PortAuthorityDates are bid due dates for tenders and the scheduled commissioning quarter for the tug.
Battery storage at Indian ports, from first tenders to the first battery-electric tug. Sizes and dates as reported in tender notices and supplier announcements.
  • V.O. Chidambaranar Port, Thoothukudi invited bids for a 2 MWh BESS, with bids due in October 2025. It then tendered an 8 MW wind project with a 5 MWh battery, bids due February 2026. The port is also a designated green hydrogen hub, and reports describe its storage as supporting steady low-carbon supply for hydrogen production.
  • Chennai Port Authority tendered a grid-connected solar project with battery storage under the renewable energy service company (RESCO) model, where a developer owns the system and the port pays for the service. Our explainer on BESS-as-a-service and RESCO contracts covers how that model works.
  • Deendayal Port, Kandla is getting India’s first fully electric tug. Its battery supplier announced a 4.4 MWh system designed for a 15-year life. A tug is mobile storage, but it still needs a high-power charging point on the quay — another large, short-duration load for the port’s grid.

These are small next to grid-scale projects. That is normal: ports are learning how storage behaves on their own networks before they scale up.

Where a battery fits on a port

  • Crane and equipment peaks. Electric cranes and yard equipment create short, sharp demand spikes. A battery can supply them so the port’s contract demand and demand charges stay lower.
  • Shore power and e-tug charging. Plugging in a ship or charging a tug adds a big block of load at unpredictable times. Storage buffers that block so the port’s substation does not have to be sized for the worst moment.
  • Firming on-site renewables. Solar and wind on port land rarely match port demand hour by hour. A battery shifts the surplus, which is the logic behind solar plus storage and wind plus storage projects.
  • Steady supply for electrolysers. Green hydrogen electrolysers prefer steady power. A battery can smooth renewable output for short periods, though it is not a substitute for long-duration supply. See hydrogen versus battery storage for where each fits.

Airports: green first, storage next

Indian airports have gone green faster than ports, but mainly through generation and sourcing rather than storage. Cochin International Airport became known as the world’s first fully solar-powered airport in 2015. Delhi’s Indira Gandhi International Airport has met its electricity needs through on-site solar and hydropower purchase since 2022. Mercom reported that eighty Indian airports had switched to 100% green energy, and official statements since then have put the number higher.

We did not find large, commissioned battery projects at Indian airports to cite. The use cases are clear, though:

  • Backup for critical systems such as airfield lighting, navigation aids and terminal IT, covering the seconds before generators pick up and short outages entirely. Our battery versus diesel genset comparison explains why a battery complements rather than replaces diesel standby.
  • Peak management for terminal air conditioning, which follows passenger peaks and the afternoon heat.
  • Electric ground equipment and vehicle charging, as baggage tractors, buses and taxis electrify. See solar, storage and EV charging.
  • Islanded microgrids at smaller or remote airfields, where a microgrid combining solar, storage and generators can improve resilience.

What this means for you

  • If you run a port or terminal: map your load profile first — crane cycles, shore power, reefer containers, night operations. The battery size comes from the peaks and the hours you need to shift, not from the solar plant’s nameplate. A 20ft containerised BESS is the usual building block at this scale.
  • If you run an airport or airfield: decide whether the battery’s main job is backup, peak cutting or renewable shifting. Each sizes differently, and trying to do all three with one undersized system disappoints on all three.
  • If you are bidding into port tenders: read the scope carefully. Port tenders often bundle wind or solar, storage and operations in one package, sometimes under RESCO terms.

Port and airport tenders, and the green port targets behind them, change by notification and from one tender to the next; verify the current terms in the specific tender documents. To see how storage would pay back on your own site’s load, try our BESS savings calculator or talk to our team.

Frequently asked questions

Why would a port need a battery if it already has solar?

Port loads are spiky — cranes lift and lower in bursts, ships plug into shore power, and electrolysers want steady supply. Solar produces in the middle of the day. A battery smooths both sides: it absorbs midday surplus and covers short, sharp peaks without raising the contract demand.

Do airports in India use battery storage today?

Mostly not at scale yet. Airports such as Cochin and Delhi went green through on-site solar and, in Delhi's case, solar plus hydropower purchase. Batteries are a natural next step for backup of critical systems and for peak management, but we did not find large commissioned airport battery projects to cite.

Can a battery replace the diesel generators at an airport or port?

Not entirely for safety-critical backup, where regulators and operators expect long-duration fuel-based standby. A battery can reduce how often generators run, cover the switchover gap instantly, and handle short outages on its own.

What is the RESCO model mentioned in port tenders?

A renewable energy service company builds, owns and operates the system and sells the energy or service to the port, so the port pays per unit rather than buying the asset upfront.