What is ACME Solar's 107.36 MW / 437.49 MWh battery storage commissioning in Rajasthan?

ACME Solar has commissioned an additional 107.36 MW / 437.49 MWh of battery energy storage in Rajasthan. pv magazine India reported it on 1 October 2026 and ESS News on 2 October. At roughly four hours of discharge at rated power, the capacity is now operating, not just planned. It follows ACME's 300 MWh Rajasthan commissioning in September.

Published 6 October 2026 · Last updated 6 October 2026 · 1 min read · By NEXGY Research Desk

More battery capacity in operation in Rajasthan, tracked as part of our tender tracker.

Commissioned pv magazine India · 1 Oct 2026

ACME Solar battery storage, Rajasthan

Power

107.36 MW

Energy

437.49 MWh

Duration

4.1 hr

Discharge signature — long-duration, runs 4.07h of 8h at rated power

Contracted Under build Commissioned

Capacity that is now operating. At about four hours it can shift a full block of solar output into the evening.

pv magazine India ↗

What it means

437.49 MWh divided by 107.36 MW gives about 4.1 hours at rated power. That puts it in the long-duration band, which suits shifting midday solar into the evening peak. The headline calls this capacity “additional”. It follows ACME’s 300 MWh commissioning in Rajasthan, which we covered in September.

Rajasthan is still where much of India’s commissioned storage is being built. Our Rajasthan storage policy note explains why. For a comparison of two-hour and four-hour systems, see BESS duration: 2-hour vs 4-hour.

Sizing storage for your own site? Run the numbers with our BESS savings calculator, or talk to our team.

Let's talk storage

Want these numbers for your site?

Send a bill or a load profile — we model it and tell you straight.