A solar-park storage call on our tender tracker that lets bidders choose between four and six hours of storage.
NHPC / BSUL BESS at Jalaun Solar Park
Power
800 MW
Energy (Config I)
4,800 MWh
Duration (Config I)
6 hr
Discharge signature — long-duration, runs 6h of 8h at rated power
800 MW of batteries in four blocks, offered as 6-hour (4,800 MWh) or 4-hour (3,200 MWh) storage alongside the park's solar.
ESS News ↗Tender at a glance
| Item | Configuration I | Configuration II |
|---|---|---|
| Solar scheduled in solar hours | 300 MW | 600 MW |
| BESS for non-solar hours | 800 MW / 4,800 MWh | 800 MW / 3,200 MWh |
| Duration (MWh ÷ MW) | 6 hours | 4 hours |
| Per block (four blocks) | 75 MW solar + 200 MW / 1,200 MWh | 150 MW solar + 200 MW / 800 MWh |
Per-block figures are from Power Peak Digest. Bidders may bid for either configuration or both. TaiyangNews says the final choice depends on the buying entity’s needs.
- Issuer: NHPC on behalf of Bundelkhand Saur Urja Ltd (BSUL), its joint venture with UPNEDA. The notice is dated 4 November 2026 (TaiyangNews, SolarQuarter).
- Model: build-own-operate. The developer buys all solar output from the park’s plants (2,419 million units a year) to charge the batteries, then schedules solar-plus-storage power at a composite tariff found by reverse auction. SolarQuarter alone quotes a solar procurement tariff of ₹2.61–2.62/kWh.
- Site and grid: batteries sit near four blocks around the Madhogarh, Pathrahi and Orai pooling substations. Power goes to the 765/400 kV ISTS substation at Orai (Power Peak Digest). The tender is technology-agnostic, with a minimum round-trip efficiency of 85% (Power Peak Digest).
- PPA and timing (Power Peak Digest): 25-year PPA with BSUL; commissioning within 18 months of the PPA effective date.
- Fees and eligibility (Power Peak Digest): EMD of ₹10 crore. Bid processing fee ₹30 lakh + GST for one block or ₹60 lakh + GST for two. Net worth of ₹353.2 crore per block (Config I) or ₹261.2 crore (Config II). One bidder group can win at most 50% of capacity and two blocks.
- Deadline: outlets differ. Power Peak Digest gives 12 December 2026, and TaiyangNews says 15 December 2026. Confirm on the Central Public Procurement Portal.
What it means
Six hours of storage is unusual in Indian tenders. It moves the park’s daytime solar into the whole evening and night peak instead of just the early evening. Our 2-hour vs 4-hour duration guide explains the trade-off. The developer also takes on solar-procurement and scheduling risk, much like an FDRE contract. See our Uttar Pradesh BESS policy guide for the state context and our FDRE tender framework explainer for comparable structures.
Weighing Config I against Config II? Talk to our bid desk, or model the economics.