Most disappointing battery projects can be traced back to the specification. If it is vague, every bid looks the same on paper, and the gaps only show up at commissioning or in year five.
A good specification does two jobs. It makes quotes directly comparable, and it turns a supplier’s promises into numbers that can be measured and enforced. This checklist works whether you are buying a single cabinet for a factory or running a utility-scale tender.
Two ways to buy: equipment or outcome
The Energy Storage Partnership’s procurement reference document, hosted by the World Bank’s ESMAP (Energy Sector Management Assistance Program), describes two ways to buy:
- Predefined system. You specify the equipment: cell chemistry, rack layout, converter rating and so on. You get control, but you also carry the design risk.
- Output-based system. You specify the result: usable energy, power, efficiency and availability at the meter. The supplier chooses the design and carries the risk of meeting the numbers.
Large Indian utility tenders are mostly output-based. They fix availability and efficiency at the point of connection and leave the design to the bidder. For most commercial and industrial (C&I) buyers, output-based is the better default. You still need a few equipment-level requirements, mainly for safety and certification.
1. Define the duty first
Everything else in the specification follows from this block. Write down:
- Rated power (kW or MW) at the point of connection, for both charging and discharging.
- Usable energy (kWh or MWh) at the point of connection, at the beginning of life and as a minimum at end of life. Never just nameplate energy.
- Duty cycle: cycles per day, typical charge and discharge windows, and rest periods. SECI’s early standalone tenders, for example, were described as needing two cycles a day with a rest period between them. Other tenders specify one, so state your own figure explicitly.
- Design life in years and total cycles.
- Site conditions: maximum and minimum ambient temperature, humidity, dust, altitude, flood level and the available footprint.
- Point of connection: voltage level, metering point and any existing solar, diesel or grid constraints.
If you are not sure of the right numbers, size the system before writing the specification. Our guide on how to size a BESS for your site walks through it.
2. Performance guarantees (the numbers you will be paid against)
This is the block most worth spending time on. State each guarantee at a defined measurement point, preferably the AC meter.
| Guarantee | What to specify | Indian reference point |
|---|---|---|
| Round-trip efficiency (RTE) | AC-to-AC, including auxiliary loads, measured monthly or at test | SECI tenders commonly require 85% monthly; CEA floor is 70% from April 2027 |
| Availability | Percentage of hours (or scheduled blocks) the system can deliver its rated power | SECI tenders commonly require 95% a year |
| Usable energy | kWh at the meter at start of life | Fixed at site acceptance |
| Degradation | Minimum usable energy by year, or end-of-life retention | Supplier-declared curve, made contractual |
| Response time and ramp rate | Seconds to full power | Needed for grid services |
| Depth of discharge | Usable window as a share of nameplate | CEA floor is 80% from April 2027 |
The Indian tenders attach money to these numbers. A SECI 50 MW / 100 MWh tender issued in August 2026 was reported to charge ₹3.50 per kWh on excess conversion losses whenever monthly RTE drops below 85%. Your contract should do something similar, scaled to your project.
The CEA amendment that takes effect on 1 April 2027 also sets a 95% minimum efficiency for the power conversion system. Ask bidders to declare their actual figures and treat the regulatory minimums as a floor. Our explainer on round-trip efficiency and degradation covers why the AC-to-AC figure is lower than the cell datasheet.
3. Battery and battery management system
Keep this block short if you are buying output-based. The essentials:
- Chemistry. LFP (lithium iron phosphate) is standard for stationary use. See LFP vs NMC.
- Declared cell make and model, with test reports, so you know what is in the box.
- Battery management system (BMS) functions: cell-level voltage and temperature monitoring, balancing, protection and data logging.
- Thermal management: liquid or air cooling, rated for your site’s maximum ambient temperature, with its power draw included in the efficiency guarantee.
4. Power conversion and grid connection
- Power conversion system (PCS) rating in kW/kVA, with reactive power capability.
- Grid code compliance with the applicable CEA connectivity standards and your DISCOM’s requirements.
- Power quality limits at the point of connection, including harmonics. See harmonics and power quality.
- Transformer and switchgear scope: who supplies them, and their ratings.
- Islanding or backup capability, if you need the battery to run your site during an outage.
5. Safety and certification
Never leave this block to the supplier. Require:
- Mandatory BIS (Bureau of Indian Standards) certifications and the relevant IEC and UL test reports for cells, modules and the system. Our BIS standards guide lists them.
- Fire detection and suppression, gas detection, explosion venting and the spacing between units.
- Compliance with the CEA safety chapter for installations above 650 V.
6. Controls, monitoring and data
- Energy management system (EMS) functions for your use case, such as peak shaving, time-of-day shifting or solar firming.
- SCADA or remote monitoring with your own access to raw data. The CEA standards require operating data to be kept for at least 90 days.
- Cybersecurity requirements for any connection to the internet.
7. Testing, warranty and commercial remedies
This block turns the earlier blocks into something enforceable:
- Factory and site acceptance tests with fixed test conditions: C-rate, temperature and state-of-charge window. See FAT, SAT and commissioning.
- Liquidated damages (pre-agreed penalties) for shortfalls in capacity, efficiency and availability.
- Warranty terms that match the performance guarantees, measured from the site-tested capacity. See BESS warranties and degradation guarantees.
- Augmentation, spares and O&M (operation and maintenance): who adds capacity to hold the guarantee, how many spares are kept on site, and response times.
If you are bidding into a public tender rather than buying, the eligibility side is covered in our BESS tender eligibility checklist.
What this means for you
- If you are a C&I buyer: a short, output-based specification covering duty, AC-side guarantees, certifications, a witnessed site test and the warranty will make quotes for systems like our C&I cabinet directly comparable.
- If you are a developer or utility: align your guarantees with the SECI pattern and the CEA floors, fix the test conditions, and price your liquidated damages so that missing a guarantee costs the supplier more than meeting it. Containerised systems such as our 20ft container are usually bought this way.
- If you have no numbers yet: start with the duty. Our BESS savings calculator gives a first estimate of size and payback, and our engineering team can review a draft specification. Get in touch.
Tender requirements and CEA standards change by notification, and every tender sets its own thresholds. Treat the reference figures here as a November 2026 snapshot and check the current document for your project.