What is Andhra Pradesh's 1,250 MW / 5,000 MWh battery storage tender?

The Andhra Pradesh Power Coordination Committee has tendered 1,250 MW / 5,000 MWh of four-hour standalone battery storage for the state's three DISCOMs, split across three sites on a build-own-operate basis. Buyers sign a 12-year storage purchase agreement, no VGF is offered, and TaiyangNews reports bids close on 23 November 2026.

Published 14 November 2026 · Last updated 14 November 2026 · 1 min read · By NEXGY Research Desk

A state DISCOM call that our news feeds missed in October. We added it to the tender tracker after our weekly check for large tenders.

Tender TaiyangNews · 14 Oct 2026

APPCC standalone BESS for AP DISCOMs

Power

1,250 MW

Energy

5,000 MWh

Duration

4 hr

Discharge signature — long-duration, runs 4h of 8h at rated power

Tendered Awarded Built Live

Three separately awarded four-hour projects for AP's DISCOMs, with a 25% green shoe and no VGF.

TaiyangNews ↗

Tender at a glance

All points below are as reported by TaiyangNews.

ProjectSiteCapacityGreen shoe (up to 25%)
1Dr. M.V. Ramana Reddy Rayalaseema Thermal Power Plant (RTPP)500 MW / 2,000 MWh125 MW / 500 MWh
2Talaricheruvu RE Project250 MW / 1,000 MWh50 MW / 200 MWh
3NP Kunta RE Project500 MW / 2,000 MWh125 MW / 500 MWh
  • Issuer: APPCC as bid coordinator for APCPDCL, APEPDCL and APSPDCL. The tender was issued on 7 October 2026.
  • Model: build-own-operate. Each project is tendered, evaluated and awarded separately, with its own tariff.
  • Operation: charge and discharge in blocks of 50 MW / 200 MWh or 100 MW / 400 MWh, alone or combined, at a 0.25C rate.
  • Contract: a 12-year Battery Energy Storage Purchase Agreement (BESPA) with each DISCOM.
  • VGF: none is available for these projects.
  • Deadline: bids are accepted until 23 November 2026. EMD and eligibility terms were not in the report, so check the tender document on the APEPDCL e-procurement site.

What it means

Without VGF, bidders must recover the full capex from a 12-year capacity tariff. That is a tougher test of battery costs than the VGF-backed tenders, as our VGF scheme explainer shows. Siting two projects at renewable parks and one at a thermal plant reuses existing grid connections. For the state context, see our Andhra Pradesh BESS policy guide, and for how DISCOMs use these assets, our DISCOM peak-shaving tenders guide.