A DISCOM-led storage tender, tracked as part of our tender tracker.
NPCL standalone BESS, Greater Noida
Power
80 MW
Energy
320 MWh
Duration
4 hr
Discharge signature — long-duration, runs 4h of 8h at rated power
A four-hour DISCOM battery at the distribution substation, transferred to NPCL for ₹1 after 12 years.
Renewable Watch ↗Tender at a glance
- Structure: four units of 20 MW / 80 MWh. Bidders may quote 20, 40, 60 or 80 MW.
- Operation: up to four hours of discharge per cycle and one full cycle a day, scheduled by NPCL. Minimum monthly availability is 95%. The tender is technology-agnostic.
- Site: identified substations in Greater Noida. NPCL provides the land on a right-to-use basis at ₹1 per plot per year.
- Model: build-own-operate-transfer (BOOT) through tariff-based competitive bidding. The battery energy storage purchase agreement (BESPA) runs for 12 years. At expiry the project transfers to NPCL for ₹1, “as is where is”.
- Commissioning: within 18 months of the BESPA effective date. A further six months is available with liquidated damages.
- Eligibility and deposits: minimum net worth of ₹74 lakh per MW quoted. EMD of ₹7.4 lakh per MW, and a performance bank guarantee of ₹18.5 lakh per MW per project. The document fee is ₹25,000 and the bid processing fee ₹1 lakh, both plus GST.
- Deadline: online bids close on 9 December 2026 (Renewable Watch). Confirm against the current tender documents.
What it means
This is storage at the distribution edge. A private DISCOM is buying four-hour capacity at its own substations to manage the evening peak, rather than relying only on a central agency. Our guide to DISCOM peak-shaving BESS tenders explains the model, and the state rules are in our Uttar Pradesh BESS policy guide. The 20 MW unit size also opens the bid to mid-sized developers who could not take on a 4 GW SECI package.
Bidding for a 20–80 MW slot? Talk to our bid desk, or model the project economics first.