The largest standalone storage call on our tender tracker this year.
SECI standalone BESS, Rajasthan + Gujarat
Power
4,000 MW
Energy
16,000 MWh
Duration
4 hr
Discharge signature — long-duration, runs 4h of 8h at rated power
16 GWh of four-hour batteries across two states, bid package by package on a build-own-operate basis.
Energetica India ↗Tender at a glance
| Item | Package I — Rajasthan | Package II — Gujarat |
|---|---|---|
| Capacity | 2,500 MW / 10,000 MWh | 1,500 MW / 6,000 MWh |
| Duration (MWh ÷ MW) | 4 hours | 4 hours |
| Bid size per bidder | 50 MW / 200 MWh to 625 MW / 2,500 MWh | 50 MW / 200 MWh to 375 MW / 1,500 MWh |
- Model: build-own-operate (BOO) through tariff-based competitive bidding, for on-demand supply. The developer finds the land, builds, owns and maintains the system. SECI signs a PPA to supply the energy to buying entities, who schedule discharge.
- PPA term: 20 years initially. Full commissioning is due within 12 months of the PPA effective date (Renewable Watch).
- Bidding: one bid per package. A bidder may bid for either package or both, and qualifies for each package separately. Bids are electronic, through the ISN-ETS portal, followed by an e-reverse auction.
- Charging: at least 51% of charging energy must come from renewable sources.
- Grid connection: the default delivery point is an ISTS substation. By mutual agreement it can move to an intra-state or STU substation.
- Central financial assistance: ₹15 lakh per MWh, about ₹2,400 crore (₹24 billion) across 16 GWh.
- Make in India: minimum local content in battery procurement, backed by an auditor-certified declaration.
- Financial eligibility: minimum net worth of ₹71.84 lakh per MW quoted.
- Technical eligibility: Route I covers battery manufacturing and supply. Route II covers experience integrating, supplying or aggregating grid-connected BESS. The minimum cumulative experience is one-tenth of the quoted capacity or 50 MWh, whichever is lower.
- Fees and deposits (per package): EMD of ₹7.184 lakh per MW. Tender document fee of ₹50,000 + GST per bidder. Bid processing fee of ₹20,000 per MW quoted + GST, capped at ₹20 lakh + GST per package. A performance bank guarantee also applies.
- Key dates: Renewable Watch reports online bid submission closes on 14 December 2026. TaiyangNews earlier gave 23 November 2026 as the last date for offline submission, so the schedule may have been revised. Confirm the current dates in the Notice Inviting Tender (NIT) and any corrigenda on the ISN-ETS portal.
What it means
16 GWh is five times the size of SECI’s 800 MW / 3,200 MWh standalone tender from October, and it keeps the same four-hour shape. Four hours is enough to charge on midday solar and cover the whole evening peak, as our guide to BESS duration: 2-hour vs 4-hour explains. Both states have large solar fleets to firm. See our Rajasthan and Gujarat policy guides.
For how these calls are usually structured, read our SECI standalone storage tenders explainer. Check the RfS and any corrigenda on SECI’s site and the ISN-ETS portal before bidding, because dates and terms can change.
Preparing a bid for this tender? Talk to our bid desk, or model the project economics first.