What is SECI's 800 MW / 3,200 MWh standalone battery storage tender?

Solar Energy Corporation of India (SECI) is seeking developers for 800 MW / 3,200 MWh of standalone battery energy storage. That is a four-hour system, built to shift energy into the evening rather than only cover short peaks. ESS News and pv magazine India reported it on 6 October 2026. It is currently at the bidding stage.

Published 6 October 2026 · Last updated 6 October 2026 · 1 min read · By NEXGY Research Desk

A new central-agency storage tender, tracked as part of our tender tracker.

Tender pv magazine India · 6 Oct 2026

SECI standalone battery storage

Power

800 MW

Energy

3,200 MWh

Duration

4 hr

Discharge signature — long-duration, runs 4h of 8h at rated power

Tendered Awarded Built Live

A four-hour standalone call from SECI. It is sized to move bulk energy into the evening, not just shave a short peak.

pv magazine India ↗

What it means

3,200 MWh over 800 MW gives a four-hour system. Storage of this duration can charge on midday solar and discharge across the whole evening peak. A two-hour asset only covers the sharpest part of that peak. It is twice the duration of POWERGRID’s 500 MW / 1,000 MWh standalone tender and similar in shape to the Serentica 600 MW / 2,400 MWh SECI PPA.

For how SECI usually structures these calls, see our explainer on SECI standalone storage tenders. As of this briefing the tender is open for bids. We will update this page with the winning bidders once SECI announces them.

Weighing a bid on a long-duration tender? Talk to our bid desk, or model the project economics first.

Let's talk storage

Want these numbers for your site?

Send a bill or a load profile — we model it and tell you straight.