Rajasthan's 1 GWh battery tender gets its bid-security terms; POWERGRID floats two Andhra Pradesh BESS tenders — 19 November 2026

Renewable Watch reports that Rajasthan's RRVUNL tender for 250 MW / 1,000 MWh of grid-forming battery storage sets a Rs 320,000 per MWh earnest money deposit and pays VGF in three tranches, with bids due 21 December 2026. POWERGRID has floated two BESS works tenders in Andhra Pradesh, and SECI's vendor empanelment closes on 30 November.

Published 19 November 2026 · Last updated 19 November 2026 · 4 min read · By NEXGY Research Desk

On this page

This edition covers the headlines since our 18 November digest. Tenders lead it again. Renewable Watch has now reported Rajasthan’s 250 MW / 1,000 MWh grid-forming battery tender from RRVUNL in full. Its report adds the bid-security and VGF payout terms that earlier coverage lacked. POWERGRID has also floated two battery tenders in Andhra Pradesh. Bids for the APPCC and SECI calls on our tender tracker close soon.

NGEL supply40,580SECI standalone16,000APPCC Andhra Pradesh5,000NHPC Jalaun (up to)4,800RRVUNL Rajasthan1,000NGEL Kerala BoS1,000
Battery energy in the largest India BESS tenders still open for bids (MWh). APPCC's 5 GWh call, linked to today's POWERGRID tenders, sits third behind NGEL and SECI.

Major tenders

Rajasthan, 1 GWh. Renewable Watch confirms that RRVUNL’s tender is a four-hour, build-own-operate battery under VGF with a fully grid-forming PCS. It also reports these terms:

  • an earnest money deposit of Rs 320,000 per MWh
  • a performance guarantee of Rs 800,000 per MWh
  • VGF paid 20% at financial close, 50% on COD and 30% after the first year

Bids close on 21 December 2026. We have added these terms to our brief.

POWERGRID, Andhra Pradesh. Mercom India reports two POWERGRID tenders for the design, supply, erection, testing and commissioning of battery storage in Andhra Pradesh. One report also covers operation and maintenance. Mercom says the tenders form part of the 1,250 MW / 5,000 MWh that APPCC has tendered. The capacity of POWERGRID’s own packages was not in the visible report, and our search of the trade press did not find it. So these tenders have no brief of their own yet. The parent APPCC programme does have one, and TaiyangNews reports its bids close on 23 November 2026.

Still open for bids. Our daily search for missed large tenders found no new call of 1 GWh or more. Each of these open tenders already has a brief:

SECI supplier empanelment

SECI’s empanelment is for battery suppliers and integrators, not project developers. Renewable Watch reports four tiers, by the largest project a vendor may bid for:

  • Tier I: up to 100 MWh
  • Tier II: up to 300 MWh
  • Tier III: up to 600 MWh
  • Tier IV: up to 1,000 MWh

Empanelled vendors then compete in project-specific RfQs and reverse auctions for DC blocks, PCS, BMS, EMS and fire suppression. No EMD is due at this stage, and applications close on 30 November 2026. Because no project capacity has been set, this has no brief.

PPAs and market

ACME Solar has signed a PPA with NTPC for a 150 MW ISTS-connected hybrid project at INR 3.21/kWh under NTPC’s Hybrid-IV tranche, pv magazine India reports. The project combines solar and wind with unspecified “energy storage solutions”, but no storage capacity was given, so it has no brief. Mercom India also ran an interview on storage as India’s next growth opportunity.

Tender terms and deadlines can change when a corrigendum is issued. Before acting, check the current bid documents on the issuing organisation’s portal. For the funding behind most of these calls, see our VGF scheme explainer and India BESS policy guide.


Want to see what a battery could save at your site? Try our BESS savings calculator, or talk to our team for a project-specific estimate.

Let's talk storage

Want these numbers for your site?